Pipeline Infrastructure Improvements Update

Friday, April 13, 2018

Monday, April 30, 2018
Dominion Energy Ohio Gas Pipeline Removal Project – P400336362
Brownell Court & East 17th Street
(City of Cleveland - Ward 3)

Expect additional traffic notices as work progresses

CLEVELAND – Dominion Energy Ohio’s gas pipeline infrastructure improvement project is scheduled to begin on Monday, April 30, 2018 and includes work on the following street:

    • Brownell Court – From East 14th Street to East 17th Street.

The project scope is to remove the existing low pressure steel mainline that is in the road to allow for construction of the new sub-grade structural retaining wall needed for the new 34 story high-rise building under construction at East 17th Street and Brownell Court.

Brownell Court between East 14th Street and East 17th Street is currently closed due to the construction of the new building. Limited access to Brownell Court from East 14th Street is currently provided for municipal services and deliveries to adjacent businesses and will continue until project completion. The work will take place Monday through Friday from 7 a.m. to 5 p.m.

This project is scheduled for completion in May 2018.

Should there be any questions, contact Dennis Scheid - Hill International at 216-701-2319.

Editor’s Note: Road construction invariably presents hazards to the public. All travelers are urged to use caution in construction zones. Public safety and the safety of workers is a top priority.

About the City of Cleveland

The City of Cleveland is committed to improving the quality of life for its residents by strengthening neighborhoods, delivering superior services, embracing diversity and making Cleveland a desirable, safe city in which to live, work, play, and do business. For more information on the City of Cleveland, visit online at www.city.cleveland.oh.us, Twitter at @cityofcleveland or Facebook at www.facebook.com/cityofcleveland.

-30-