Pipeline Infrastructure Improvements Update

Thursday, January 11, 2018

Monday, January 22, 2018
Dominion East Ohio Gas Pipeline Infrastructure Replacement Project – PIR 2138
Vineyard Avenue & Warner Road
(City of Cleveland Ward 2)

Expect additional traffic notices as work progresses

CLEVELAND – Pipeline infrastructure improvements begin on Monday, January 22, 2018 and include work on the following street:

  • Vineyard Avenue – North side from Warner Road westerly to the end of the street.

The project scope is to replace the old steel mainline with new plastic mainline in the sidewalk area. One lane of traffic will be maintained at all times on Vineyard Avenue with traffic control personnel in the work zone(s) directing traffic. Access to adjacent driveways will be maintained throughout construction and the work will take place Monday through Friday from 7:00 a.m. to 5:00 p.m.

This project is scheduled for completion by the end of February. Temporary, 2” thick sidewalk will be installed until permanent sidewalk can be installed in the spring of 2018. Final grading and landscaping will immediately follow permanent sidewalk installation.

Should there be any questions, contact Dennis Scheid - Hill International at 216-701-2319.

Editor’s Note: Road construction invariably presents hazards to the public. All travelers are urged to use caution in construction zones. Public safety and the safety of workers is a top priority.

About the City of Cleveland

The City of Cleveland is committed to improving the quality of life for its residents by strengthening neighborhoods, delivering superior services, embracing diversity and making Cleveland a desirable, safe city in which to live, work, play, and do business. For more information on the City of Cleveland, visit online at www.city.cleveland.oh.us, Twitter at @cityofcleveland or Facebook at www.facebook.com/cityofcleveland.

###